Meeting Reminder

This is a reminder that during the Lane-repair project, the Board is holding meetings for all residents every Monday at 7:30 p.m. via Zoom. Drop in at tonight's meeting if you have questions on the construction progress. To join tonight’s Zoom meeting at 7:30 p.m., please use the login info we sent in the September 18 email.

Recap of Recent Activity

The contractors finished installing the wood for the concrete forms. They then worked on installing rebar and executing repairs to the vertical steel columns — and any other necessary steel repairs within the project scope. The two trees on North Street, flanking the front of Mayfair Lane, were pruned in order for the concrete contractors to position their concrete boom across the upper Lane.

Concrete pouring will begin soon. Waterproofing will follow (in early October). Drain augering and a cleaning of the garden beds will occur prior to the waterproofing stage. TRM is aware of problematic drains that neighbors have reported to the Board; please be assured that contractors will address these drainage issues just prior to waterproofing. TRM ordered the fieldstone (option 3, which 11 households voted on). After the waterproof membrane is installed, the next step is for contractors to install the fieldstone.

Also, TRM will provide us with a newer Gantt chart once they have applied the latest updates to it. Parking remains prohibited on the lower Lane.