Dear Mayfair Lane neighbors,
We have updates for you:
Quarterly Assessments
Please note that starting in 2024, we will operate on a different fiscal calendar. Therefore, quarterly assessment payments will now be due on the first day of:
February
May
August
November
Plumbing Work
Thank you for being understanding and flexible with the parking situation this past weekend while plumbers were on the Lane. They were able to finish PVC pipe installation on sections 2 and 3 of the Lane.
Section 1: No Parking on 12/16 During Day
The plumbers will be returning to section 1 (front-third section) of Mayfair Lane on Saturday (12/16) to install PVC piping on the underside of the Lane. So, starting at 7 a.m. on 12/16, cars in section 1 cannot be parked in the exterior spaces of the lower Lane. Garage parking will not be affected; you can navigate to and from your garage with no impediments. Section 1 can resume normal parking at 7 p.m. on 12/16.
Electrical Work
The electricians have finished installing all light fixtures on the lower Lane! They are now working on restoring power to some of the pagodas on the upper Lane that were moved during the project.
Upper Lane Walking Surface
TRM estimates that there are approximately 2-3 weeks of work remaining. (There was a delay while TRM awaited a third-party waterproofing inspector to approve the garden-pit waterproofing.) In section 3, the white vinyl-finish coating has been applied to the waterproofing membrane. Contractors have begun staging for fieldstone installation in section 3. The work to finish waterproofing and fieldstone installation on sections 2 and 1 will follow.
Pressure Washing
At the conclusion of the project, TRM will ensure that the lower Lane is pressure washed to remove construction debris, dirt and paint drippings.
Thank you, as always, for your patience and flexibility — especially as the holiday season is underway!
Respectfully,
Your Mayfair Lane Board